Follow the progress of each building step by step
Site 1
Site 2
Site 3
Site 4
Site 5
Building 1
Building 2
October 2026
September 2026
August 2026
January 2026
December 2025
November 2025
October 2025
September 2025
August 2025
July 2025
June 2025
May 2025
April 2025
October 2026
September 2026
August 2026
January 2026
December 2025
November 2025
October 2025
September 2025
August 2025
July 2025
June 2025
Follow the progress of each building step by step
Site 1
Site 2
Site 3
Site 4
Site 5
Building 1
Building 2
100%
Earthworks
100%
Foundation
100%
Frame and monolithic works
100%
Brickwork
100%
Roofing
100%
Windows / Terraces
(PL) 75%
Interior finishing works
75%
Facade
100%
Plastering work
100%
Strainer
100%
Elevator installation
10%
Internal networks
25%
External networks
100%
Earthworks
100%
Foundation
100%
Frame and monolithic works
100%
Brickwork
85%
Roofing work
50%
Windows / Terraces
50%
Plastering work
50%
Strainer
25%
External networks
Request a Consultation